Loudoun supervisors put data center votes on hold for up to a year

Loudoun County supervisors voted Tuesday, Nov. 17, to hold off for up to 12 months on data center and electrical substation applications that need their approval, a delay that could reach 33 active cases.
A majority of the Board of Supervisors backed the pause, which they made retroactive to Sept. 15.
Developers can keep filing data center and substation proposals in the meantime. No pending application will go inactive.
"A previous legal opinion from the Loudoun County Attorney indicated that a moratorium to stop all data center approvals is not legal," the county said in its news release on the vote.
Work on the applications goes on, short of a final decision. County staff will keep reviewing them and setting public hearings before the Planning Commission, while "the Board's intent is to pause any Board of Supervisors public hearings and Board votes on such applications," the county wrote.
Those votes carry more weight in Loudoun than they once did. Supervisors earlier ended by-right data center development, so every data center project now needs a board vote through the special exception process.
There's a limit on how long the board can wait. Under Virginia law, it has one year to act on such applications, counted from the day they first reach the Planning Commission.
Supervisors may consider exceptions for projects tied to the reliability of the electric grid, or for those whose legal deadline for a decision is close to running out.
Some projects aren't covered at all. Legislative applications for land in the Route 28 Tax District are exempt, and so are applications handled through administrative processes.
Behind the delay is a rewrite of the county's data center rules, called the Data Center Standards and Locations project. It proposes changes to the 2019 Comprehensive Plan and the Zoning Ordinance on how data centers are built and where they can go.
Supervisors wanted to give the county time "to complete the ongoing review of current data center policies and regulations," the release said.
Loudoun expects that review to be finished by summer 2027. Once supervisors adopt the plan and zoning amendments it produces, the pause ends.